b.
DOCUMENTS
a. Approved shop drawings related to the work
b. Materials Manufacturer Technical Data Sheet
c. Approved Method of Statement for the Construction
c.
RELEVANT PRODUCTS & TOOLS
a. Plaxit CP – 150 Cement Plaster Render
b. Jotun paints (Mat)
c. A-Z Super Sealer
d. Fosroc (Brush bond) waterproofing
e. Normal Cement
f. Blocks – 200mmx200mm hollow bloks
g. Ready mix – slump 100 20N OPC
d.
MISCELLANEOUS MATERIALS
a. Green mesh serves backing to catch the sprayed cement
plaster
b. 8mmØ
corrugated steel bar for reinforcement
c. Angle bars
d. Tie wires
e. Chicken wire mesh
f. Welding Rods
e.
TOOLS
a. Carving tools – specially designed to make cracks & texture
of rock
b. Texturing mats
c. Finishing Trowels
d. Wire Cutter
e. Grinder
f. Steel Cutter
f.
EQUIPMENTS
a. Mixing Pump PFTG5 Super state
of the art machine designed to withstand the
tough
condition of construction sites
b. Welding machine
g. PREPARATION
a. Clearing the area. i.e. excavation, lay-outing, etc.
b. Delivery of materials & equipments to be used on site
2.
SITE REQUIREMENTS AND CONDITION
a. Access
Rockworks are usually done
before the completion of all the landscaping works and other
trades. It is considered as a decorative finishing item.
Consequently, there should be free access to the installation
area and no vehicles, rough usage or other trades mixing and
fabrication.
b. Electrical
Electrical supply should be
provided in the job-site specifically single and 3 phase line
c. Water
Supply of water should always be available on the job-site
d. Products Handling & Storage
·
All materials shall be delivered to project site in sealed
container or bags with polyethylene inner bags
·
All materials shall be stored undercover and be protected for
re-excessive changes in temperature & humidity. Opened
bags should be utilized same day
TALLATION
PROCEDURE
a. Sub-grades
Base fro lagoons should be well
compacted and backfilled before pouring concrete
b. Concrete
Place the concrete blinding 50mm thick
c. Forms
Lay-outing of hollow core concrete blocks for the boundary of
the lagoon
d. Reinforcement
Forming the steel structures as prescribed on shop drawings
e. Plumbing works
Lay-out/installation of pipes for the water system of the
waterfall
f. Electrical
·
Lay-out electrical pipes for under water lights
·
Lay-out electrical pipe for motor pump/filter & switches
·
Power supply pipe from main line
g. Plastering
·
Spray 1st coat of Plaxit CP – 150 Cement Plaster
Render in the whole structure
·
Spray 2nd coat of Plaxit CP – 150 Cement Plaster
Render in preparation for
the application of the waterproofing
h. Place concrete flooring to
cover plumbing works & electrical works on the
lagoon
i. Waterproofing
·
Apply 2 coats of fosroc brush bond for water proofing and
spray 1 coat of Plaxit CP – 150 to cover water proofing
j. Finishing/Texturing/Carving
·
Spray Plaxit CP – 150 on the structure with the desired
thickness for the texturing & carving
k. Curing
After carving, at least 10 days curing
l. Coloring
·
Spray the 1st coat of Jotun paint for the base
·
Apply/spray the final color of the rocks to attain good
effects of a natural rock
m. Applying of Sealer to protect
the paint |